If any part of the CQP is suspended, who bears all delay costs?

Prepare for the FDOT Quality Control Manager Class Test. Practice with quizzes and multiple-choice questions, complete with hints and detailed explanations. Ensure your success with our comprehensive study tools!

The correct answer indicates that the contractor bears all delay costs if any part of the Construction Quality Program (CQP) is suspended. This is based on the principle that the contractor is responsible for managing and executing the project within the agreed-upon timeline and specifications. When a part of the CQP is suspended, it implies that the contractor's planned activities are disrupted, leading to delays.

Under typical contractual arrangements, especially within the framework set by the Florida Department of Transportation, it is the contractor's responsibility to ensure that the project progresses without unnecessary disruptions. The terms and conditions outlined in the contract often specify that the contractor assumes liability for the consequences of delays that are not attributable to actions or inactions of the project owner or external entities. In this context, it reinforces the contractor's accountability in managing time and costs effectively throughout the project lifecycle.

The other choices suggest that the burden of delay costs could fall on stakeholders such as the project owner, the federal government, or state authorities, but such allocations are not typically consistent with common contractual practices related to construction project management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy